Commenting on the government’s decision on Wednesday, Minister of Energy Luis Sanchez said that “administrative errors were found during a revision of the report,” adding that YPBF would issue a fresh public tender “in the next few months.”
“Between the contract award and signing, it’s common to annul a contract. That means we’ll draft a new contract. We’ll need to take some time,” Sanchez also said.
Construction of the plant was expected to commence in 2017 and be completed by 2021.
Once operations commence, the capacity of the plant will be 250,000 tpy of polypropylene. About 80-90% of the output is set to be exported while the remainder is planned to be used domestically.
In December 2016, YPFB chose two finalists in the bidding process for FEED-EPC work of a planned propylene and polypropylene plant.
Out of five bidding companies, a conglomerate of Samsung Engineering-Intecsa Ingeniería Industrial known as UTE Polipropileno Yacuiba and a Tecnimont-Técnicas Reunidas consortium known as UTE TCM-TR were qualified for the final stage of the bidding. The latter tie-up was announced the winner in May 2017.
The UK's hydrocarbons regulator has awarded 31 new exploration licences in the country's North Sea waters, Reuters reported on Friday Read More
ExxonMobil announced the closing of its USD 60-billion acquisition of Pioneer Natural Resources on Friday, a move that solidifies its… Read More
BP-Eni joint venture Azule Energy has entered a strategic farm-in agreement with Rhino Resources in Namibia's offshore Orange Basin, the… Read More
Africa-focused energy group Chariot has spudded the RZK-1 exploration well on the Gaufrette prospect at the Loukos Onshore licence in… Read More
Touchstone Exploration has acquired Trinidad-focused Trinity Exploration & Production in an all-shares deal, the Canadian upstream player said on Wednesday Read More
ExxonMobil is "optimistic and pushing forward" with the Rovuma LNG project in Mozambique and eyes an FID by the year's… Read More
This website uses cookies.