Freeport LNG seeks fourth train project extension

USA
Freeport LNG has requested a 26-month extension from state regulators on construction of a fourth train at its facility in Texas, Reuters announced on Wednesday.

In May 2019, permission was received from the US Federal Regulatory Commission to commence building the new train and related infrastructure but was met with delays due to challenges caused by the COVID-19 pandemic.

In September 2020, the authorities extended construction to May 2026.

The latest request will would see works extended until August 2028.

The Freeport LNG terminal currently consists of three trains with a capacity of 15.45 million tonnes per year.

Recent Posts

Chariot starts gas drilling campaign in Morocco

Africa-focused energy group Chariot has spudded the RZK-1 exploration well on the Gaufrette prospect at the Loukos Onshore licence in… Read More

33 mins ago

Touchstone acquires Trinidad E&P player Trinity

Touchstone Exploration has acquired Trinidad-focused Trinity Exploration & Production in an all-shares deal, the Canadian upstream player said on Wednesday Read More

10 hours ago

ExxonMobil “optimistic and pushing forward” with Mozambique’s Rovuma LNG

ExxonMobil is "optimistic and pushing forward" with the Rovuma LNG project in Mozambique and eyes an FID by the year's… Read More

17 hours ago

SLB OneSubsea, Subsea7 sign long-term deal with Equinor

SLB OneSubsea and Subsea7 have signed a long-term strategic collaboration agreement with Equinor and begun work on two of its… Read More

18 hours ago

Presight AI takes 49% stake in ADNOC energy AI player

Presight has acquired a 51% shareholding in AIQ, an energy-focused AI player founded by ADNOC and G42, the companies announced… Read More

18 hours ago

Wood wins TotalEnergies North Sea flare recovery work

UK engineering contractor Wood has been awarded a decarbonisation project by TotalEnergies to support flare gas recovery in the North… Read More

1 day ago

This website uses cookies.