Barakah Nuclear Energy Plant

Barakah Nuclear Energy Plant

The Barakah Nuclear Energy Plant is located in Al Dhafra in the emirate of Abu Dhabi, around 53 kilometres west-southwest of the city of Ruwais. Since the launch of its operations in 2020, the Barakah Nuclear Energy Plant has been delivering safe, clean and reliable electricity to the UAE grid.

PROGRESS: Having been connected to the UAE’s transmission grid in August 2020, units 1 and 2 of the plant are completed. As of September 2020, the construction of units 3 and 4 stood at 93% and 87%, respectively.

Timeline of construction

JOINT VENTURE:

In October 2016, ENEC and KEPCO signed a JV agreement for a long-term partnership and co-operation on the UAE’s Peaceful Nuclear Energy Programme. With the signing, two new companies were established:

> Barakah One Company is an independent subsidiary owned by both companies which represents the commercial and financial interests of the Barakah project. ENEC is the majority owner with an 82% stake, while KEPCO holds the remaining 18%.

Joint venture organogram

> Nawah Energy Company is a subsidiary of ENEC and is mandated to operate and maintain Barakah’s units. KEPCO has an 18% stake, while ENEC holds 82%.

KEY FACTS: 

> Installed capacity: The plant consists of four identical APR1400 reactors housed in four separate units, with a total power generation capacity of up to 5.6 GW.

> Demand: Will supply up to 25% of the UAE’s electricity needs once fully operational.

> Milestone: The Barakah plant is the first nuclear energy station to be constructed in the Arab world.

> Carbon footprint: The plant will eliminate the release of 21 million tonnes of carbon emissions per year, equivalent to removing 3.2 million cars from the roads.

> Clean energy: The Barakah plant is the largest source of clean baseload electricity in the country.

Map of the plant

ABOUT THE REACTORS:

Model: APR1400 nuclear reactors

Reactor design: APR1400 is a pressurised-water reactor designed by KEPCO

Power capacity: Each reactor can generate up to 1.4 GW of electricity

SOURCE: ENEC

Recent Posts

A strategic approach to service optimisation

Russell Boodoo, regional business development manager at TOSL Engineering, talks to The Energy Year about the company’s role in supporting… Read More

2 days ago

Experience brings business in Kuwait

Suresh Pillai, CEO of Mark Technologies, talks to The Energy Year about the company’s involvement in Jurassic gas production and… Read More

3 days ago

Enhanced well services in Trinidad and Tobago

Narvin Salick, district manager of Gyrodata Trinidad, talks to The Energy Year about how the company has been impacted by… Read More

4 days ago

Chevron: 70 years of commitment in Angola

Billy Lacobie, CABGOC’s managing director for Southern Africa, talks to The Energy Year about recent strategic and operational developments in… Read More

5 days ago

Angola’s power generation and electrification ambitions

Angola is working hard to increase its power generation capacity by boosting hydro and solar energy, as well as linking… Read More

5 days ago

Turbocharging Kuwait’s oil production

Jasem Al Nouri, deputy managing director of Nouri Industrial Establishment, talks to The Energy Year about the company’s long-standing commitment… Read More

6 days ago

This website uses cookies.