Mexico’s electricity market, long monopolised by the Federal Electricity Commission (CFE), has undergone a major shift parallel to the changes underway in the upstream oil and gas industry as part of the country's energy reform. CFE director Enrique Ochoa Reza talks to TOGY about the commission’s $17-billion plan for the largest electricity grid overhaul in the country’s history.
What investments in infrastructure does Mexico’s electricity grid need most?
The CFE has more than $17 billion in investments planned for priority infrastructure projects that aim to fulfil Mexico’s booming electricity demand. These include 11 natural gas pipelines ($5.2 billion), seven thermoelectric power plant conversions ($200 million), seven combined-cycle power plants ($6 billion), 15 renewable power generation projects ($4.8 billion) and a combination of seven transmission lines and nine distribution projects ($1 billion).
The company’s renewable energy initiatives comprise two hydropower projects, five geothermal projects and eight wind projects.
Between 2015 and 2016, the CFE plans to complete 11 natural gas pipelines, which will span a length of about 2,300 kilometres. The tendering process for the seven combined-cycle power plants is ongoing. Three power plants have been awarded to three different energy companies as of June 2015. Once completed, these plants will bring an additional 5.3 GW of capacity to Mexico’s electricity grid.
How can Mexico mitigate the electricity losses in its distribution network?
The CFE was able to reduce its energy losses from 16 percent in 2012 to 14 percent in 2014. The commission is targeting the reduction of losses to 10-11 percent by 2018.
As part of the CFE’s nine distribution projects, the installation of 910,400 metering infrastructure devices and 20,500 transformers and the construction of 1,437 circuit kilometres will be prioritised. These modernisation projects represent a total investment of around $1 billion. They will further reduce losses associated with electricity distribution, yet more is needed.
As a result of ongoing infrastructure modernisation, the CFE’s operational losses are being reduced. In 2014, the commission saw an operating loss of $2.1 billion, representing a 30-percent decrease compared to 2013.
Some factors that are contributing to these developments include the increasing natural gas supply to power generation facilities from pipelines such as Los Ramones, as well as a year that saw a high level of rainfall.
High rainfall kept the level of hydroelectricity production high throughout 2014. This in turn led to efficient electricity production and lower prices for consumers. In 2014, electricity sales rose by more than 5 percent to $19.6 billion.
For more news and features from Mexico, click here.
TOGY talks to Sylvain Itté, French Ambassador to Angola, about the strong economic and cultural ties between the two countries,… Read More
TOGY talks to Li Patrik, director of energy, environment, infrastructure at the China-Britain Business Council (CBBC), about the difficulties of… Read More
TOGY talks to Río Negro province Secretary of Hydrocarbons Sebastian Caldiero about policies implemented by the provincial government to manage… Read More
TOGY talks to Heba Filobbos, area manager of the Northern Gulf for Halliburton, about the company’s experience working as an… Read More
TOGY talks to Christopher Gunson, partner at Amereller, about the oil and gas industry in the UAE and the surrounding… Read More
TOGY talks to Graeme Taylor, Vice President for Angola at Halliburton, about forecasted stabilisation, onshore potential and the qualities required… Read More
This website uses cookies.